Mobile crusher and excavators processing demolition arisings Watford
Demolition Crushing Bulk Dig

Demolition & Crushing

Watford, Hertfordshire
Live Job — Updated Weekly

The Job

A major demolition and enabling package in Watford: breaking out and grubbing up deep buried structures, processing reinforced concrete, and crushing arisings into reusable aggregate on site. This page is a running diary — we add to it as the job moves on.

Job Diary

Week commencing 15 September 2026

Deep Digs & More Crushing

The crusher kept turning demolition arisings into aggregate stockpiles while the excavators worked the deep dig, grubbing up reinforced concrete foundations and old basement walls within the retained excavation.

Crusher and excavator producing recycled aggregate Watford Grubbing up deep reinforced concrete foundations Watford Excavator exposing buried concrete obstruction Watford Pulveriser processing reinforced concrete with dust suppression Watford
Week commencing 8 September 2026

Crusher On Site

The tracked crusher arrived and got straight to work. Excavators charged it with broken-out concrete across the cleared platform, producing large stockpiles of crushed material for reuse — recycling the site's own arisings instead of carting them away.

Site-wide view of mobile crusher and three excavators Watford Excavators charging the crusher across the demolition platform JCB 140X loading the crusher between crushed stone stockpiles Excavator cutting the bulk dig to formation Watford
Late August 2026

Breaking Out Buried Foundations

Massive buried mass-concrete and brick foundations came out with the breaker, with water dust suppression keeping the site clean inside a hoarded town-centre compound.

Breaker with dust suppression breaking out buried concrete Watford Hydraulic breaker splitting a massive buried foundation block Breaking out mass concrete beside a new kerb line Watford Twin excavators working the deep dig side by side Watford
Summer 2026

Where It Started — Car Park Breakout

The job began with our 14-tonne JCB 140X stripping and breaking out the existing car park for reconstruction.

JCB tracked excavator loading broken tarmac Watford Car park breakout underway Watford