External works around a modular school building in Ebbsfleet, Kent: supporting the building while foundations were upgraded, then new drainage runs, concrete paths, slabs and access steps around the full perimeter. This page is a running diary — we add to it as the job moves on.
The wrap-around channel drainage, downpipe connections, fresh tarmac paths and new galvanised access steps are complete around the building — a tidy finish to the external works.
Formwork struck and concrete down: new slabs and paths poured around the building and the steel access tower, with drainage runs connected and rebar dowels tying new edges into the pours.
The modular building was carefully supported on engineering-brick piers while the foundations beneath were upgraded — precise, methodical work under a live structure.